Primero Building Project 2007-2009

Bonds and Mill Levy Overrides

Design Team Members

Pictures of Project

Sketches of Buildings

Neenan Design Contract

Neenan Construction Contract

CTL-Thompson Soils Tests:

Initial Soils Tests

Load Bearing Tests

Construction Schedule 4-16-2008 (476 KB)

EPA Facility Information

Colorado Oil & Gas Commission Report:

Commission's Report

Primero Seepage Study June 2007 (6 MB)

Mold Assessment Report (487 KB)

Neenan Budget (8/07) (21 KB)

. . . . . . . . Asbestos Abatement Phase 1 Completed March 27 . . . . . . . Well Field for Ground Source Geo-Thermal Heat Pump System Finished April 30 . . . . . . . . Sprinkler, Well, and Irrigation Water Work Underway in Early May . . . . . . . . Building To Be Packed and Moved Out by May 22 . . . . . . . . Summer Construction Begins May 23. . . . . . . . Office in Modular Bldg May 23 - Aug. 31 . . . . . . . .

PRIMERO DESIGN TEAM

Mike Duran, Board President
Dave Huey, Board Treasurer
LaDonna Moltrer, Board Secretary
Jubal Incitti, Board Member
Gerald Gabbard, Superintendent of Schools
Bill Naccarato, Principal
Eric Davies, Business Manager
Lee Daugherty, Owner's Representative
Laurie Corsentino, Accountability Chair
Jessica Berry, Graduate
Kaylee Putnam, Student
Roger Diller, Industrial Arts
Darryl Abeyta, Transportation
Jerry Lucero, Custodian
Debra Pacheco, Business/Technology


THE NEENAN COMPANY - FORT COLLINS
ARCHISTRUCTION: DESIGN - BUILDERS
Ugljesa Janjic, Architect
Joe Glaze, Pre-construction Manager
Robert Maunton, Construction Superintendent
Mike King, Project Manager
Tammy Dorsey, Interior Design

ENNOVATE - AURORA (HVAC)
Alan Hill, Senior Engineer
Aaron Skroch, Engineer
Heidi Svenkeson, Engineer
Scott Logan, Project Manager

NORTHSTAR ENGINEERING - PUEBLO
SITE SURVEYS & WASTEWATER TREATMENT
Tamara Muhic, Engineer

BRET'S ELECTRIC - DENVER Bret Martin

GARLAND ROOFING COMPANY - DENVER
Eric Tscharner

Fred Dixon, Computer Cowboy - Network Admin.

Fayne Long, FreComm - Telephone

CTL-Thompson - Colorado Springs (Soils Tests)

All Phase Environmental - Pueblo
(Mold/Asbestos/Radon Tests)

Hazardous Waste, Inc. - Pueblo
Asbestos Abatement


Water Works Plus, LLC - Weston
Sprinkler, Well & Irrigation Systems


Webber Well Service
Well Repair


CanAmerica Corp. - Colorado Springs
Well Field Drilling


Purgatoire Valley Construction Co. - Trinidad
Housing Construction


Diamond T Enterprises, Inc. - Trinidad
Demolition of Houses and Old Bus Barn


View of current school building from south (4/08). Dirt piles are for baseball outfield project.

BONDS AND MILL LEVY OVERRIDES

^ TOP ^

The District was very grateful that voters approved three financial ballot issues in the November 6, 2007 general election:

(1) A $10.7 million bond to upgrade the facilities, including renovating the existing building, making important additions for industrial arts-art-music, a new roof, HVAC upgrades for ventilations, heating and air conditioning, a community center, a track, and a wastewater treatment plant; and replacing staff housing with 7 new units;

(2) A $350,000 per year general fund mill levy override to stabilize our operational budget; and

(3) A $140,000 per year transportation fund mill levy override to help with excess pupil transportation costs.

The District is in the Design Phase of the Project with the Neenan Company, its archistructure design build firm. Principle contractors include Ennovate (HVAC), NorthStar Engineering of Pueblo (wastewater treatment plant), Bret's Electric (electrical upgrades), and Garland Roofing (new metal standing seam, seamless roof.)

See the Design-Construction Budget and Current Month Investments and Expenditures of Bonds - click here

Sketches of New Additions and Renovations at Primero

^ TOP ^

Images and materials provided and copyrighted by the Neenan Company and are used with permission.

Site Plan

Industrial Arts-Art-Music Wing

New Front Entrance

Cafeteria Addition

Floor Plan - Renovations

Community Center Idea

Needs

See larger PDF files of the pictures below by clicking on these links:

You need Adobe Acrobat if you wish to download these files.

Otherwise, you can scroll down and see them posted on this page.

If you do not have Adobe Acrobat, click here to download it.

^ TOP ^

Aerial View of School Property. Additions in Shaded Areas. Additions include a new industrial arts-art-music wing on the southwest corner of the building, a cafeteria expansion, housing structures providing 8 units for staff, and a community center. Neenan is managing the industrial arts addition, interior renovations, wastewater treatment plant, HVAC upgrades, cafeteria expansion, and track. The District is managing the houses and community center construction.

^ TOP ^

Aerial View of Additions and Renovations. Additions include an industrial arts-art-music wing in the lower left of the drawing. Renovations include upgrading the HVAC system, installing a new standing seam-seamless metal roof, relocating the office, updating the science room to be a true science lab, relocating the high school computer lab and guidance offices, creating staff and preschool bathrooms, and expanding the library with after hours access.

^ TOP ^

New front entrance to school - 3/5/08

^ TOP ^

Cafeteria expansion - 3/5/08

^ TOP ^

East Views of Industrial Arts-Art-Music Wing Addition - 3/5/08 ^ TOP ^

Southeast view of new industrial arts-art-music wing - 3/5/08 ^ TOP ^

Overhead view of industrial arts-art-music wing - 3/5/08

^ TOP ^

Community Center Idea

Needs To Be Addressed By This Building Project:

^ TOP ^

Health and Safety:

  1. The current building has poor air quality and no ventilation. Every room tested had unsafe levels of carbon dioxide. There is mold present in some areas due to our leaking roof.

  2. The current roof leaks in multiple locations and has created mold in some spots. The roof needs replacement.

  3. The office is not located by the main entrance of the building. It needs relocation to provide a safer and more welcoming entrance to the building for parents, visitors and guests.

  4. Our floor tiles have asbestos and need abatement and replacement. (Phase 1 abatement: March 21-30, 2008)

  5. Our science classroom is not a true science lab and does not have proper safety equipment, including ventilation, a modern fume hood, gas jets, and an eyewash station.

Wear and tear and energy efficiency:

  1. The main gym floor has only one sanding left and the bleachers are old and falling apart. The floor and bleachers need replacement since this is a major community area and sports arena and event hall.

  2. Almost all windows are single-pane and inefficient. Our boiler system is old and inefficient. We have numerous propane tanks scattered over the property that should be consolidated.

  3. The industrial arts program is housed in an old, drafty pole barn that used to house the buses. We currently can offer woods for a small group of students and occasionally welding. The pole barn needs to be demolished and rebuilt. The proposed new industrial arts-art-music addition includes a wood shop, welding shop, autobody and auto mechanics shop, a paint shop, an industrial arts classroom, an art room with kiln area and pottery studio, a music classroom with a practice room and storage, and male and female bathrooms, including showers.

 